Malvern Boys College Boarding House
Click on an above image to enlarge.
Malvern Boys College Boarding House
Client
Speller Metcalfe
Construction of new boarding house
Malvern Scaffolding was appointed the scaffold contractor on this project for Speller Metcalfe. We worked closely with Speller Metcalfe from an early stage in planning the logistics of supplying materials to a very confined site. The site’s primary means of supply is through the use of a tower crane to get materials onto site. With all trades onsite wanting use of the crane it has meant our site supervisor, Stuart Barrett, has had to work closely with the management team on site to hit delivery times, order scaffold onto site and oversee the safe erection of the scaffold. To help in the process of lifting the scaffold by crane, his team was put through a slingers/signalmen course.
Scope of works
• 3000m external scaffold fully boarded
• 200m hand-railing
• Birdcage scaffolds
• 6 ladder access towers
• Lift shafts/stairwells
• 7 crane loading bays
Programme
45 weeks