Designed Birdcage Loading Tower for Industrial Roofing Works

Client: Central Roofing and Building Services

Our client Central Roofing is one of largest roofing firms in the region, often working as Main Contractors. They have been undertaking a rolling programme of roof upgrades at this Specialist Industrial facility for many years. In order to overhaul the 150m length roof monitors and clerestory windows on the highest roof on site, they required a 19.5m high x 15mwide x 8m deep loading platform with hoist for a 9 month programme of works.

The designed scaffold also had an integral Layher system stairtower, fully enclosed heavy-duty rubbish chute and maintained pedestrian access at ground level. It was designed specifically to impose no load to the upper sections of the building.

Project Duration: 9 months

Project Value: Confidential